Road Resurfacing Schedule

Construction Season Starts Here!

We are ready! Our construction season has just started and weather permitting, this will be the City of Elkhart Street Department milling schedule from Monday April 6th through Thursday April 9th, 2026. Vehicles should be removed from the street prior to 7am and not return until after 7pm OR until barricades are removed. Sidewalks and/or alleyways will be accessible to and from your home, but street access will be prohibited during the milling process.

4/6 Monday: Milling

  1. Hazel St.-Hively Ave. to Perkins Ave.
  2. Warren St.- Hively Ave. to Perkins Ave.
  3. Lowell St.- Hively Ave. to Perkins Ave.
  4. Eddy St.- Hively Ave. to Perkins Ave.

4/7 Tuesday: Milling

  1. Minnie St.-Eddy St. thru Hazel St.
  2. Perkins St.-Sterling Ave. thru Hazel St.
  3. Primrose Ave.-Perkins Ave. to north Cul De Sac
  4. Bent Ct.-Sterling Ave. to Primrose Ave.

4/8 Wednesday: Milling

  1. Bent Ct.-Sterling Ave. to Primrose Ave.
  2. Sterling Ave.-Hively Ave. to Lusher Ave.

4/9 Thursday: Milling

  1. Desmond Ave.-Prairie Ave. to west Dead End
  2. Harrison St.-Oakland Ave. to Franklin St
  3. Mason St.-Freemont St. to Thomas St.